Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DBB/CMAR
# of Projects: 1
100% of the Results

Background informationProject Created: June 22, 2009

Project Name: PA Turnpike/I-95 Interchange Project
Year in Operation:
Sector: Transportation
Subsector: Roads, Electronic Vehicle ID / Toll Collection
Status: Design / Construction
Type: New Facility
Description: The project will provide a direct connection between the PA Turnpike and I-95, also adding a new toll plaza and including mainline widening.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments:

Project Locations

Address:
City: Midway
State: Pennsylvania
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: The project will be executed on site of the PA Turnpike and I-95.
Checkbox Checked Environmental Clearance: An environmental impact study was conducted for the Interchange Project. Environmental clearance obtained through design process by PA Tpke.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: The project is funded by the PA Turnpike and the U.S Department of Transportation.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
10
0
Forms
Description
 
 

Project Value (If and As Known)

Date of Estimated Project Value: September 1, 2004
Project Value
Hard Cost
Hard & Soft Costs
Total
$500 Million - 2 Billion US