Background informationProject Created: July 14, 2009

Project Name: Ilisu Dam, Tigris River Turkey
Year in Operation:
Sector: Water & Waste
Subsector: Water
Status: Design / Construction
Type: New Facility
Description: The dam is one of 21 dams included in the Southeastern Anatolia Project of Turkey, with the largest associated hydroelectric power plant, with an expected power capacity of 1,200 MW.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: The project has been opposed by a variety of groups, including those who would be displaced by the construction, and by the Iraqi government, which petitioned European backers to withdraw funding for the project.

Project Locations

Address:
City: Batman
State:
Country: Turkey, Republic of

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: The land is owned by the Republic of Turkey.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: In March 2007, the governments of Germany, Switzerland, and Austria agreed to support companies from their countries to assist in the building of the Ilisu dam. Export Credit Agencies (ECAs) are public or semi-public institutions that support domestic companies in business overseas by granting government-backed loans, guarantees and insurance were used to encourage these agreements. In July of 2009, these three countries withdrew their funding for the dam project due to assertions of human rights violations, making it unclear how or if construction will continue.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
7
0
Forms
Description
 
 

Project Value (If and As Known)

Date of Estimated Project Value: August 5, 2006
Project Value
Hard Cost
Hard & Soft Costs
Total
$500 Million - 2 Billion US