Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DBOM Partially Public Finance
# of Projects: 1
100% of the Results

Background informationProject Created: July 27, 2009

Project Name: A1 Darrington to Dishforth
Year in Operation: 2003
Sector: Transportation
Subsector: Roads
Status: In Operation
Type: New Facility
Description: The project includes the operations and maintenance of 33 miles of the A1 between Darrington and Dishforth as well as the DB of 15 miles of new dual 3 lane highway.
Delivery Method as described in the country where it's located: Public Private Partnership
Is the project still active: Yes
Comments: PFI, DBFO

Project Locations

Address:
City: Yorkshire
State:
Country: United Kingdom of Great Britain & Northern Ireland

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: The land is owned by the Crown government underneath the Department for Transport (DfT).
Checkbox Checked Revenue Stream (Cash Flow) Protected Through Long Term Commitment(s) of Public Sponsor(s): The private sector entity will operate and maintain the motorway for a concession period of 33 years.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: The project is financed by the Crown government.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Is there an independant checking engineer? Yes
Project Finance Method: All or Partially By Public Sponsor

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Combined Term: Initial Design, Construction, O&M Period
33
0
Forms
Description
 
 

Project Value (If and As Known)

Date of Estimated Project Value: February 25, 2003
Project Value
Hard Cost
Hard & Soft Costs
Construction
$250 Million - 1 Billion US