Background informationProject Created: August 19, 2009

Project Name: Ribeirão das Neves prison facility
Year in Operation:
Sector: Buildings
Subsector: Prison
Status: Design / Construction
Type: New Facility
Description: The first prison facility in Brazil to be built by means of a Public-Private Partnership. Such prision will be located in Ribeirão das Neves, State of Minas Gerais, and will have the capacity of 3.040 inmates.
Delivery Method as described in the country where it's located: Public Private Partnership
Is the project still active: Yes
Comments: The private partners will build the facility without any governmental participation, and maintain it for the 27 following years through a monthly payment by the government.

Project Locations

Address:
City: Ribeirão das Neves
State:
Country: Brazil, Federative Republic of

Souces of Project Support (Non-monetary)

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: The government will pay R$74,63 to the concessionaire per inmate, per day (about US$ 3.250.000 monthly, with the prison at full capacity).

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Is there an independent checking engineer? Yes
Project Finance Method: All By Private Sponsor

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Combined Term: Initial Design, Construction, O&M Period
27
0
Forms
Description
 
 

Project Value (If and As Known)

Date of Estimated Project Value: August 19, 2009
Project Value
Hard Cost
Hard & Soft Costs
Construction
$100-250 Million US
(none)
Total
< $200 Million US
(none)