Background informationProject Created: March 11, 2010

Project Name: Twin Spans I-10 (New Orleans)
Year in Operation: 2010
Sector: Transportation
Subsector: Roads, Bridge
Status: In Operation
Type: New Facility
Description: Emergency repair of I-10 crossing over Lake Pontchartrain east of New Orleans following heavy damage to the crossing by Hurricane Katrina in Aug 2005. The new "twin span" crossing is built to the south of the old crossing, will carry 3 travel lanes in each direction, with 12 foot shoulders on each side of these lanes.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: Initial emergency repairs of $30 million performed to make crossing passable. Replacement project is fully funded by federal government through Katrina relief funds.

Project Locations

Address:
City: New Orleans
State: Louisiana
Country: United States of America

Address:
City: Slidell
State: Louisiana
Country: United States of America

Address: South Point
City: New Orleans
State: Louisiana
Country: United States of America

Address:
City: Eden Isle
State: Louisiana
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: Adjacent to existing ROW. This is Interstate 10, a major east west highway across the USA.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers

Arrow Right
Checkbox Checked

Direct Cash Support

Arrow Right
Checkbox Checked

From Other Public Entities - Direct Grant of Appropriated Public Funds: $800 million in emergency relief grants from Federal govt.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Manager At Risk while design is in process.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
6
0
Forms
Description
Mandatory Statutory Form
 

Project Value (If and As Known)

Date of Estimated Project Value: August 1, 2006
Project Value
Hard Cost
Hard & Soft Costs
Construction
$250 Million - 1 Billion US
(none)