Background informationProject Created: April 26, 2010

Project Name: Expansion of John Wayne Airport, Orange Cty, CA
Year in Operation:
Sector: Transportation
Subsector: Airport, Transportation Terminal
Status: Design / Construction
Type: Substantial Alteration of Existing Facility
Description: Three year $543 million dollar project to add a third 282,000 sq ft passenger terminal, new parking structure for 2000 cars, central utility plant, and imporvement to two existing terminals. Expansion will incresae annual capacity to 10.8 million passengers per year, and increase gates from 14 to 20.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: Package of projects, each being delivered on DBB basis.

Project Locations

Address: 18900 S Airport Way
City: Santa Ana
State: California
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: New terminal is on site of old parking structure, which was demolished.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers

Arrow Right
Checkbox Checked

Direct Cash Support

Arrow Right
Checkbox Checked

From Public Sponsor of Project - Direct Expenditure of Appropriated Public Funds: Public airport began collecting a $4.50 per passenger fee in 2006 that is expected to fund about 75% of the expansion. The fee is in place thorugh 2022.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
3
0
Forms
Description
Other
 

Project Value (If and As Known)

Date of Estimated Project Value: April 26, 2010
Project Value
Hard Cost
Hard & Soft Costs
Construction
$250 Million - 1 Billion US
(none)