Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DBB/CMAR
# of Projects: 1
100% of the Results

Background informationProject Created: June 1, 2010

Project Name: Margaret Hunt Hill Bridge (Dallas/Ft.Worth)
Year in Operation:
Sector: Transportation
Subsector: Bridge
Status: Design / Construction
Type: New Facility
Description: Signature bridge, among five new bridges, being constructed across the Dallas Floodway, as part of the Trinity Corridor Project in Dallas. Designed by Santiago Calatrava, the structure will be 1870ft in overall length, with six lanes for traffic, and a 1200 foot central span.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: Formerly the Woodall Rodgetrs Extension Bridge. Design completed in April 2006, Construction contract awarded in October 2006. Completion expected in mid-2010.

Project Locations

Address: Continental Avenue
City: Dallas
State: Texas
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers

Arrow Right
Checkbox Checked

Direct Cash Support: $115 million is contract cost for the birdge and connections outside the levee. Dallas' contribution is capped at $28 million, from Trinity Corridor bond funds. Hunt family donated $12million to the corridor project. Federal and state agencies, and other private donations will provide the balance of funding for the structure.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
4
1
Forms
Description
Mandatory Statutory Form
State format. 

Project Value (If and As Known)

Date of Estimated Project Value: October 1, 2006
Project Value
Hard Cost
Hard & Soft Costs
Construction
$100-250 Million US
$100-250 Million US