Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DB
# of Projects: 1
100% of the Results

Background informationProject Created: August 10, 2010

Project Name: Ridgecrest (CA) Naval Technology Center
Year in Operation:
Sector: Buildings
Subsector: Other Government Building
Status: Design / Construction
Type: New Facility
Description: P-745 Weapons Armament Technology Center at the Naval Air Weapons Station (NAWS) China Lake. Mojave desert technical and management support offices, general engineering laboratories, information facility, and conference center at Navy's China Lake base. State of the art, two story project also includes more than 600 above ground parking stalls, extensively landscaped open space, and meets US Green Building Council's LLEED Silver certification, with potential for Gold certification.
Delivery Method as described in the country where it's located: Design Build
Is the project still active: Yes
Comments:

Project Locations

Address:
City: Ridgecrest
State: California
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: Already under control of US Navy.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers

Arrow Right
Checkbox Checked

Direct Cash Support

Arrow Right
Checkbox Checked

From Public Sponsor of Project - Direct Expenditure of Appropriated Public Funds: Appropriated federal funding. $68 million.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for both initial design and construction with a single entity. Public Owner operates and maintains the resulting facility.
Is there an independant checking engineer? Yes

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
1
0
Forms
Description
Mandatory Statutory Form
Typical US format for two-step federal design build.  

Project Value (If and As Known)

Date of Estimated Project Value: June 14, 2010
Project Value
Hard Cost
Hard & Soft Costs
Design
< $10 Million US
(none)
Construction
< $100 Million US
(none)
Total
< $200 Million US
(none)