Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DB
# of Projects: 1
100% of the Results

Background informationProject Created: October 30, 2010

Project Name: Fairplay (CO) WWTP
Year in Operation: 2008
Sector: Water & Waste
Subsector: Wastewater
Status: In Operation
Type: Repositioning of Existing Facility
Description: Because of the high elevation and extremely cold temperatures inherent in the city of Fairplay, Colorado, new ammonia limits set by the state were not being met by the town’s existing lagoon-type wastewater treatment plant which relies on warmer temperatures to be effective. As a replacement, it was recommended that an integrated fixed-film activated sludge treatment facility, capable of biological nutrient removal, be design and built. This would reduce process time from 60 days to 12 hours. This recommendation was executed and the plant was been operating effectively since Winter of 2008.
Delivery Method as described in the country where it's located: Design Build
Is the project still active: Yes
Comments:

Project Locations

Address:
City: Fairplay
State: Colorado
Country: United States of America

Address: 1507 County Road 16, Fairplay, CO 80440
City: Fairplay
State: Colorado
Country: United States of America

Address: 1507 County Road 16
City: Fairplay
State: Colorado
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Land: 35 acres of land and Right of Way for the project were already owned by the Fairplay Sanitation District and ready to be built on. There was no charge to the Design-Builder to build on the site
Checkbox Checked Environmental Clearance: The measures were minimal as the site is considered “Clean”

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: The Fairplay Sanitation District provided all the capital through small amounts of cash on hand, and securing public grants and revenue bonds.

Arrow Right
Checkbox Checked

Direct Cash Support: The Fairplay Sanitation had some cash in hand. The Fairplay Sanitation District was able to secure $3.4 million in funding for the intial delivery of the project through the sale of Revenue bonds through the George K. Baum and Associates Bank.

Arrow Right
Checkbox Checked

From Other Public Entities - Direct Grant of Appropriated Public Funds: Also received grant money from Department of Local Affairs (DOLA) for roughly $500k. The Colorado Department of Public Health (CDPH) also contributed a $110k grant for site clean-up after construction was complete.

Arrow Right
Checkbox Checked

Credit Enhancements

Arrow Right
Checkbox Checked

From Other Public Entities: The District was also able to secure approximately $2 million through a State Revolving Fund (SRF) Loan.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for both initial design and construction with a single entity. Public Owner operates and maintains the resulting facility.
Is there an independant checking engineer? No

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
1
1
Forms
Description
Other
Design-Build Institute of America (DBIA) Standard Contract Type for Design-Build delivery 

Project Value (If and As Known)

Date of Estimated Project Value: October 30, 2010
Project Value
Hard Cost
Hard & Soft Costs
Total
< $200 Million US