Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DB
# of Projects: 1
100% of the Results

Background informationProject Created: October 31, 2010

Project Name: ASU (Phoenix) Nursing Health Renov. II
Year in Operation: 2009
Sector: Buildings
Subsector: School
Status: In Operation
Type: New Facility
Description: The Arizona State University College of Nursing and Health Innovation, Phase II (ASU NHII) project is designed to fulfill projected growth and is therefore designed for future expansion opportunities. This new multi-use project is approximately 84,000 SF and 5 stories high. It contains classrooms, office and administrative spaces, a 200-seat conference center and a 60-seat computer classroom laboratory.
Delivery Method as described in the country where it's located: Design Build
Is the project still active: Yes
Comments:

Project Locations

Address:
City: Phoenix
State: Arizona
Country: United States of America

Address: 411 N. Central Ave
City: Phoenix
State: Arizona
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Land: The city of Phoenix owns the land for the project, but did not charge the contractor an extra cost to build on it. The city will operate and maintain the project after construction, and lease the building to Arizona State University
Checkbox Checked Environmental Clearance: Some of the environmental clearance and mitigation measures that were necessary included elements such as asbestos and lead paint abatement, meeting ADA regulations, building near historical canals and uncovering significant archaeological finds. The building was also able to achieve a LEED gold rating in sustainability.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: Before the design and construction of the project, voters in the city of phoenix approved $250 million in bonds to enhance education. ASU also contributed capital to the project.

Arrow Right
Checkbox Checked

Direct Cash Support: The city of Phoenix was able to fully fund the project with bonded cash-on-hand from voter approved bonds and financing contributed by ASU.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for both initial design and construction with a single entity. Public Owner operates and maintains the resulting facility.
Is there an independant checking engineer? No

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
1
1
Forms
Description
Other
City of Phoenix’s own standard form contract 

Project Value (If and As Known)

Date of Estimated Project Value: October 31, 2010
Project Value
Hard Cost
Hard & Soft Costs
Total
< $200 Million US
(none)