Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DBB/CMAR
# of Projects: 1
100% of the Results

Background informationProject Created: December 2, 2010

Project Name: Rotterdam Centraal RR Station Reconstruction
Year in Operation:
Sector: Transportation
Subsector: Transportation Terminal, Rail, Roads
Status: Design / Construction
Type: Substantial Alteration of Existing Facility
Description: Demolition of 1960's portion of the existing Centraal station in Rotterdam, to be followed by construction of rehabilitated inner-city transportation interchange in Rotterdam, with mix of ultra-modern architecture, massive open space above and around the rail platforms, green space, an underground rail station, access to the metro, parking for cars, bicycles, bus lanes, car lanes, taxi lanes.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: Design through collaboration among multiple architectural firms. Separate demolition by contract. Intensive coordination with hydraulic engineers throughout. Separate construction by multiple contractors.

Project Locations

Address: Weena 688
City: Rotterdam
State:
Country: Netherlands, Kingdom of the

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers

Arrow Right
Checkbox Checked

Direct Cash Support: The Rotterdam Central Station Project is funded by Rotterdam Municipal Authority; the Ministry of Transport; Public Works and Water Management; the Ministry of Housing, Spatial Planning and the Environment; NS Dutch Railways; Prorail; and Stadsregio Rotterdam.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
4
0
Forms
Description
 
 

Project Value (If and As Known)

Date of Estimated Project Value: October 6, 2010
Project Value
Hard Cost
Hard & Soft Costs
Construction
$250 Million - 1 Billion US