Background informationProject Created: December 15, 2010

Project Name: Route 52 Causeway Cape May NJ
Year in Operation:
Sector: Transportation
Subsector: Bridge, Roads
Status: Design / Construction
Type: New Facility
Description: $400 million replacement and reconstruction of 2.5 mile long Route 52 Causeway from Ocean City (NJ) to Somers Point (NJ). The project replaces an aging crossing that includes two drawbridges with tall, fixed spans 55 feet over the water. Bicyclist and pedestrians had been forbidden to use the existing crossing, which has no shoulders and no sidewalks. The new bridge includes a 10-foot wide bike path.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: Lead designer Michael Baker Jr., Inc., with 15 other technical subconsultants. Two different teams of construction contractors are building the projects in distinct phases. 60% of project is being built from the water using crane bages.

Project Locations

Address: 1050 Shore Rd
City: Somers Point
State: New Jersey
Country: United States of America

Address: 900 Palen Avenue
City: Ocean City
State: New Jersey
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: Adjacent to existing causeway, over land controlled by the state.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: Funded by state of New Jersey.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
4
0
Forms
Description
Mandatory Statutory Form
state format 

Project Value (If and As Known)

Date of Estimated Project Value: November 15, 2010
Project Value
Hard Cost
Hard & Soft Costs
Construction
$250 Million - 1 Billion US
(none)