Background informationProject Created: December 26, 2010

Project Name: Durham (ORE) Phase 4 WWTP Expansion
Year in Operation: 2007
Sector: Water & Waste
Subsector: Wastewater
Status: In Operation
Type: New Facility
Description: The project involved the design and construction of a 180 MGD influent pump station for an advanced wastewater treatment facility. The features of the facility included dual wetwells/drywells, each with two 25-mgd and one 40-mgd pumps, a self cleaning wetwell design, flywheels on the pump motors for surge control, and the first pump station in the country to be silver LEED certified.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments:

Project Locations

Address: 16580 SW 85th Avenue, Tigard, OR 97224
City: Tigard
State: Oregon
Country: United States of America

Address: 16580 SW 85th Avenue
City: Tigard
State: Oregon
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: Site controlled by utility.
Checkbox Checked Environmental Clearance: The project was required to obtain a number of Erosion Control and Wetlands Permits prior to execution

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: The project was funded through a combination of System Development Charges, increased user rates, cash on hand, and the sale of municipal bonds.

Arrow Right
Checkbox Checked

Direct Cash Support: Debt repaid through rates collected from users.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
3
0
Forms
Description
US EJCDC
 

Project Value (If and As Known)

Date of Estimated Project Value: December 26, 2010
Project Value
Hard Cost
Hard & Soft Costs
Total