Background informationProject Created: April 7, 2011

Project Name: kcICON (Kansas City Interstate Connector)
Year in Operation: 2011
Sector: Transportation
Subsector: Bridge, Roads
Status: In Operation
Type: Substantial Alteration of Existing Facility
Description: $245 million reconstruction of four miles of Interstate 29/35 from north of Route 210 (Armour Road) in North Kansas City over the Missouri River into the northeast corner of downtown Kansas City Mo.
Delivery Method as described in the country where it's located: Design Build
Is the project still active: Yes
Comments:

Project Locations

Address: Armour Road
City: North Kansas City
State: Kansas
Country: United States of America

Address:
City: Kansas
State: Missouri
Country: United States of America

Address: Armour Road
City: North Kansas City
State: Missouri
Country: United States of America

Address: 1200 Independence Ave
City: Kansas
State: Missouri
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: Replacement of existing bridge over Missouri River. Reconstruction of existing Interstate approaches and connections.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers

Arrow Right
Checkbox Checked

Direct Cash Support

Arrow Right
Checkbox Checked

From Public Sponsor of Project - Direct Expenditure of Appropriated Public Funds: MoDOT

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for both initial design and construction with a single entity. Public Owner operates and maintains the resulting facility.
Is there an independant checking engineer? Yes

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
3
1
Forms
Description
Other
Mo DOT 

Project Value (If and As Known)

Date of Estimated Project Value: April 7, 2011
Project Value
Hard Cost
Hard & Soft Costs
Design
$10-25 Million US
(none)
Construction
$100-250 Million US
(none)
Total
$200-500 Million US
(none)