Background informationProject Created: November 28, 2011

Project Name: Lake Champlain Bridge
Year in Operation: 2011
Sector: Transportation
Subsector: Roads, Bridge
Status: In Operation
Type: New Facility
Description: New bridge between New York and Vermont, designed and built in 2.25 years to replaced a previous brigde built in 1927 that was condemned by the NYS DOT in 2009 and demolished. The new structure includes a main span that was lifted into place by the contractor -- Flatiron Constructors.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: States of NY and Vermont entered into a joint agreement to complete the demolition of the previous bridge and the substitution of a new structure. Designed by a consultant first, and then constructed by Flatiron.

Project Locations

Address:
City: Crown Point
State: New York
Country: United States of America

Address:
City: Addison
State: Vermont
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Access to Land: Replacement bridge.
Checkbox Checked Environmental Clearance: Replacement bridge. Federal and state environmental approvals obtained by the states of NY and Vermont. This was an emergency replacement. Travel restricted while the former bridge was in a condemned state, and during demolition and reconstruction.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: NYS and Vermont.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
2
1
Forms
Description
 
 

Project Value (If and As Known)

Date of Estimated Project Value: November 28, 2011
Project Value
Hard Cost
Hard & Soft Costs
Design
< $10 Million US
(none)
Construction
< $100 Million US
(none)