Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DBB/CMAR
# of Projects: 1
100% of the Results

Background informationProject Created: April 10, 2012

Project Name: Houston St (NYC) Roadway Reconstruction
Year in Operation: 2009
Sector: Transportation
Subsector: Roads, Wastewater, Water
Status: In Operation
Type: Substantial Alteration of Existing Facility
Description: Roadway reconstruction, Houston Street from West Street to the Bowery, includes sewer and water main work.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: Standard Consultant

Project Locations

Address: Houston St. at West St.
City: New York
State: New York
Country: United States of America

Address: Houston St. at Bowery St.
City: New York
State: New York
Country: United States of America

Address: 350 W. Houston St.
City: New York
State: New York
Country: United States of America

Address: 76 E. Houston St.
City: New York
State: New York
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Land: Provided by the city
Checkbox Checked Environmental Clearance: Through the city

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers

Arrow Right
Checkbox Checked

Direct Cash Support: From city appropriations

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design
X

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
7
3
Forms
Description
Other
Prescribed by the city 

Project Value (If and As Known)

Date of Estimated Project Value: January 1, 2010
Project Value
Hard Cost
Hard & Soft Costs
Design
< $10 Million US
(none)
Construction
< $100 Million US
(none)
Total
< $200 Million US
(none)
Array ( [0] => stdClass Object ( [project_id] => 552 [component_id] => 4 [qbs] => 1 [rfq] => 0 [rfp] => 0 [ifb] => 0 [up] => 0 [active] => 1 ) )

Warning!!!

You are about to delete: .

Confirm Deletion Cancel