Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DB
# of Projects: 1
100% of the Results

Background informationProject Created: January 1, 2017

Project Name: Withlacoochee (GA) Treatment Plant Upgarde
Year in Operation: 2016
Sector: Water & Waste
Subsector: Wastewater
Status: In Operation
Type: Substantial Alteration of Existing Facility
Description: Substantial upgrade of facilities constructed in the early 1980's to treat wastewater before discharge in the Withlacoochee River, part of the Suwanee River Basin. The upgraded facilites have a capacity of 8.0 MGD as an average annual daily flow with capability to treat peak flows up to 12.0 MGD. During a 2009 flood, the old facility was out of commission for over a week, and was not restored to full operations for over a month. The new plant is located on a 75 acre parcel 1 miles away and 100 feet higher
Delivery Method as described in the country where it's located: Design Build
Is the project still active: Yes
Comments: Because the plant was knocked out temporarily was flooding in 2009, the replacement project was let as a "Fast Track Design Build" project.

Project Locations

Address: 3352 Wetherington Lane
City: Valdosta
State: Georgia
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Land: City purchased

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers: $23 Million project cost for design and build.

Arrow Right
Checkbox Checked

Direct Cash Support: This is part of the City's long term Special Purpose Local Option Sales Tax (SPLOST) funding mechanism. The City has expended $167 million for water/wastewater projects from SPLOT proceeds, system revenues, bonds, and Georgia Environmental Finance Authority (GEFA) loans since 1992.

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for both initial design and construction with a single entity. Public Owner operates and maintains the resulting facility.
Is there an independant checking engineer? No

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
3
0
Forms
Description
To Be Determined
Fast Track Design Build contract awarded to Parson on June, 19, 2014, with estimated completion date of August 2017. Actual completion was June, 2016. 

Project Value (If and As Known)

Date of Estimated Project Value: June 1, 2016
Project Value
Hard Cost
Hard & Soft Costs
Pre-Feasibility (Public Sponsor Expense)
(none)
> $50 Million US
Design
< $10 Million US
< $10 Million US
Construction
< $100 Million US
< $100 Million US
Total
< $200 Million US
< $200 Million US

Warning!!!