Project Details

✔ Project has been published!

Results Chart for Delivery Method and Financing

Delivery Method

DBB/CMAR
# of Projects: 1
100% of the Results

Background informationProject Created: June 14, 2017

Project Name: Emergency I-85 (Atlanta) Collapsed Bridge Replacement
Year in Operation: 2017
Sector: Transportation
Subsector: Roads, Bridge
Status: In Operation
Type: Repositioning of Existing Facility
Description: After a March 30 fire in a GA DOT temporary storage facility beneath a portion of Interstate 85 in the Buckhead section of Atlanta, this major artery was severed by a bridge collapse that day. By April 2, GA DOT engineers had provided plans for redesigned beams to fabricators to get this emergency repair of 700 feet of elevated interstate roadway underway (350 feet long and four lanes wide in both the northbound and southbound directions). The original bridges were built in 1984, and were of a different design then prevalent. The project was completed in 45 days.
Delivery Method as described in the country where it's located: Design Bid Build
Is the project still active: Yes
Comments: Design was done internally by GA DOT. Contractor was picked, on an emergency basis, without competition through an IFB. 90% of the costs of the repair are expected to be reimbursed to GA DOT by the US DOT.

Project Locations

Address: 2121 Piedmont Rd NE
City: Atlanta
State: Georgia
Country: United States of America

Souces of Project Support (Non-monetary)

Checkbox Checked Environmental Clearance: Emergency response to repair existing facility.

Souces of Project Support (Monetary)

Checkbox Checked

From Public (Government) Sources to Producers

Arrow Right
Checkbox Checked

Direct Cash Support: 10 percent of $16.6 million emergency project expected to be funded by GA DOT. Demolition costs expected at $1.6 million, $12 million for construction cost, and up to $3.1 million in incentive payments to the contractor C.W. Matthews to finish early.

Arrow Right
Checkbox Checked

From Other Public Entities - Direct Grant of Appropriated Public Funds: 90% reimbursed by US DOT. (approximately $15 M)

Project Delivery & Finance Method

Project Delivery:
All Public Finance. Public Sponsor contracts for initial design, and separately contracts for initial construction. Public Owner operates and maintains the resulting facility.
Construction Manager At Risk Variants: Public Sponsor contracts with Construction Contractor after Design is Complete.

Procurement Approach

Project Component
Qualifications
Based Selection
Request for
Qualifications
Request for
Proposals
Invitation
for Bids
Unsolicited
Proposals
Design

Term for Key Components & Forms of Contract

Project Component
Years
Quarters
Initial Design and Construction
0
1
Forms
Description
Don't Know
Design was done internally by GA DOT. Contractor selected without competition, to save time. Incentives offered for early completion. 

Project Value (If and As Known)

Date of Estimated Project Value: November 30, -0001
Project Value
Hard Cost
Hard & Soft Costs
Pre-Feasibility (Public Sponsor Expense)
(none)
> $50 Million US
Design
< $10 Million US
< $10 Million US
Construction
< $100 Million US
< $100 Million US
Total
< $200 Million US
< $200 Million US

Warning!!!

You are about to delete: .

Confirm Deletion Cancel